Situated on the River Doyang, a tributary of the River Brahmaputra, this Project with a capacity of 3 X 25 MW and an estimated annual generation of 227 Million Units was commissioned on the 2nd week of July'2000. The Project is located in Wokha District of Nagaland. |
 |
Overview of Doyang Project |
|
|
|
|
|
| |
| |
| |
| FEATURES |
| |
|
Name ::
|
DOYANG HYDRO ELECTRIC PLANT |
| |
|
Capacity ::
|
75 MW (3 X 25 MW) |
| |
|
Location ::
|
District - Wokha,Nagaland, PIN - 797100 |
| |
|
Approach ::
|
By Road 30 KM from Wokha town, 72 KM From Golaghat in Assam |
| |
|
Design Energy :: |
227 MU ,90% dependable year |
| |
|
Date of Commissioning ::
|
Unit - I (8-July-2000) |
| Unit - II (5-July-2000) |
| Unit - III (29-June-2000) |
| |
|
| Beneficiary States :: |
Assam, Arunachal Pradesh, Manipur, Meghalaya, Mizoram, Nagaland and Tripura |
| |
|
| Technical Features :: |
|
| |
| Dam |
Type :: Rock Filled
Height :: 87.50 m
Length :: 462 m
|
| Tunnel |
1 no. Steel lined HRT with double bifurcation, 5.92m dia, 427.86 m long |
| Penstock |
| Design Head |
67.0 m |
|
| |
|
| |
Evacuation System :: Two 132 kV lines of PGCIL to Dimapur. Two 132 kV lines of Govt of Nagaland (Kohima & Mokuksung) |
| |
|
| |
|
|
| |
| |
| |
| ACHIEVEMENT |
|
| |
Generation of DHEP was 112% of Design Energy in the year 2004-05.
|
| |
| |
| |
| |
|
|
| |
| |
| STATUS OF GENERATION: |
| |
a) |
Generation during May 2010 |
|
3.5 MU |
b) |
Generation during 2009-2010(01/04/2009 to 31/03/2010 ) |
: |
180.41 MU |
|
|
|
|
|
|
| |
| |
| |
| |
| |
| CONTACT PERSON |
| |
HEAD OF PROJECT |
Project Head |
Rajat C Sharma |
Designation |
GM(E/M) |
Telephone (O) |
03860 245013 |
Telephone (R) |
03860 2450180 |
Email |
rajatsharma@neepco.gov.in |
|
| |
| |
|