SALIENT FEATURES
Name KAMENG HYDRO ELECTRIC PROJECT
Location Arunachal Pradesh ,West Kameng District
Approach

The nearest Airport is Tezpur and the nearest Rail Head is Bhalukpong.

Capacity 600 MW ( 4x150 )
Energy Generation 3952 MU
Project Cost
Rs.2496.90 crores
Tariff Rate Levellised tariff : Rs 1.23/Unit, 1st Year tariff : Rs 1.48/Unit
Year of Commissioning /Completion Schedule
March 2011
^top
 
LAYOUT  
 
TECHNICAL FEATURES KAMENG HYDRO ELECTRIC PROJECT
 
  • Height of Concrete Gravity Dam on Bichom River = 69 m
  • Height of Concrete Gravity Dam on Tenga River = 24.50 m.
  • Length of HRT (having 6.70m dia. Modified Horse Shoe Shape Tunnel) =14.527 Km.
  • Surge Shaft (Restricted Orifice Type) having 13m dia (with upper expansion Chamber 25m dia) and 69.35m depth.
  • Power House (Semi under ground type): Size: 120.00 m x 37.30 m having 4 units of 150 MW each.
  • Type of Turbine: Vertical Francis Turbine.
 
 
^top
 
PRESENT STATUS (AS ON 30.06.2010)
 

Sl.

No

ACTIVITY

Unit

Total Qty.

Cumulative

progress

Remarks

1

BICHOM DAM

 

 

 

 

i)

Excavation

 

Cum

495000

442511.00

 

 

ii)

 

Concreting

 

Cum

 

328341

 

6803.18

 

2

 

i)

 

DIVERSION TUNNEL

(L= 350.23m)

Open excavation of Portal & open channel

 

Cum

 

130834.41

 

58178.00

 

 

The work of D/T is in progress.

ii)

Boring

Rm

350

150.50

3

TENGA DAM

 

 

 

 

i)

Excavation

Cum

102000

89970.00

Work is in progress.

ii)

Concreting

Cum

63000

650.00

 

4

HEAD RACE TUNNEL

(BORING)

 

 

 

 

i)

Face - I

Rm

785

716.20

 

ii)

Face - II

Rm

4315

1302.00

Work is in progress.

iii)

Face – III

Rm

4123

2269.61

Work is in progress.

iv

Face – IV

Rm

143

124.00

 

v)

Face - V

Rm

280

243.10

 

vi)

Face – VI

Rm

2404

1161.50

Work is in progress.

vii)

Face - VII

Rm

2295

2295

Completed on 27.05.10

viii)

Face - VIII

Rm

132.50

132.50

Completed on 28.12.06

5

HIGH PRESSURE TUNNEL (HPT)

 

 

 

 

i)

U/G excavation from VerticalShaft-5 ( Face – XI) Ch.1654 m

 

Rm

 

360

 

331.50

 

Boring is done by heading and benching method.

 

ii)

Face – X (Ch.1621m)

 

Rm

 

327

 

281.75

Boring is done by heading and benching method.

 

iii)

Open excavation of surface penstock

 

Cum

 

407504

 

125333

 

iv)

Vertical Shaft -2

( ch.1278m)

 

Rm

 

96

 

89.93

 

Boring in progress.

v)

Vertical Shaft – 3

( ch.1278m)

 

Rm

 

98.4

 

80.00

 

Boring in progress.

vi)

Vertical Shaft – 4

( ch.1622m)

 

Rm

 

45

 

1.00

 

 

vii)

Vertical Shaft – 5

( ch. 1655m)

 

Rm

 

42

 

19.20

 

Boring in progress.

6

SURGE SHAFT

 

 

 

 

 

i)

 

Lining of Surge Shaft

 

Rm

 

70

 

30.55

 

7

POWER HOUSE

 

 

 

 

i)

Excavation

Cum

1050000

1049842

Progress is hold due to incessant rain.

 

ii)

 

Concreting

 

Cum

 

30600

 

11696.11

 

Work is in progress.

8

Hydro Mech Works: (HPT)

 

 

 

 

i)

 Fabrication

MT

13000

2740.22

 

ii)

ii) Erection

MT

13000

672.46

 

9

Electro – Mechanical works

(Package – V)

·      Earth mat laying within the service bay completed and in progress towards the unit pit alongwith the progress of PH civil works. Pit liner segments, Stay rings, DT elbow liner, Stator frame assembly, Spiral testing device, Air duct cover, Stator frame and core assembly, Top guide bearing pads, limit switch (instrument) EOT crane, Brake piping conduit, CW pipings, Top guide pads, Spiral segments, guide apparatus, pole fixing, guide pad, pivot ring, Top cover etc reached and unloaded at Bhalukpong/ Tippi/ Kimi site. EOT crane girder

    (1 set) reached at Kimi site.

 

10

 

132 KV & 400 KV Switchyard –

(Package – VI)

 

Detailed work order issued to M/s Techno Electric & Egg. Co. Ltd, Kolkata on 30.03.09. Demarcation of Switchyard area completed.

11

Transformer

Package - VII

 

Detail work order issued to M/s BHEL on 04.06.08

^top
CONTACT PERSON
BICHOM KIMI
Name: M Deka D K Nath
Designation: Head Of Project , Executive Director (C) Head Of Project
Tel No: 03782 207189 03787 273504
Email : hopbdc@neepco.gov.in dknath@neepco.gov.in
^top
 
 
 
Click on this Link For a Detailed Photo Gallery of Kameng Hydro Electric Project
^top

|| About Us | Completed Projects | On Going Projects | Future Projects | Commercial | Chairman's & Directors' Reports | Neepco's Socio Economic Contibution | Environment | Events | Power Potential in the North East | Tender Notices | Feedback | MOU | RTI ||

Neepco home Page HOME         BackBACK