Logo

North Eastern Electric Power Corporation Limited

(A Government of India Enterprise)


KOPILI HYDRO ELECTRIC PLANT

 

  A Profile

 
INTRODUCTION FEATURES ACHIEVEMENT STATUS OF GENERATION CONTACT PERSON
 
 

INTRODUCTION
 

Located on the River Kopili in the North Cachar Hills District of Assam, the Kopili Hydro Electric Project was the maiden venture of NEEPCO when it came into existence in 1976.

Khandong And Kopili POWER STATION:

The first stage of Kopili Hydro Electric Plant has two numbers of dam and dyke systems for creating two reservoirs, one on the Kopili River and the other on the Umrong stream, a tributary of the Kopili. Water from the Kopili reservoir is utilised in the Khandong power station through a 2759 metre long tunnel to generate 50 MW (2 X 25 MW) of power. The tail water from this powerhouse is led to the Umrong reservoir. The water from Umrong reservoir is taken through a 5473 metre long tunnel to the Kopili power station to generate 100 MW (2 X 50 MW) of power.

The first stage extension of the Plant envisaged setting up two additional 50 MW units at Kopili power station, provisions for which were already kept during the first stage development of the project. The Units III and IV under this extension scheme were commissioned in March, 1997 and June, 1997 respectively. The total installed capacity of the Kopili power station thus went up to 200 MW and that of the project as whole to 250 MW. The raising of the Umrong reservoir by 7.6 m was taken up to meet the demand for more water for two additional 50 MW units of first stage extension.

KHEP Stage II POWER STATION:

The second stage of the Kopili Hydro Electric Plant involves a powerhouse to generate additional 25 MW of power by utilising water from the Khandong reservoir through a 481 m long water conductor system, provision of which was kept as a by-pass conduit from the surge shaft in the Khandong tunnel. The water from the second stage powerhouse will go to the Umrong reservoir for utilisation in the Kopili power station

 
Overview of Kopili
 

^ top


 
 
 
 
FEATURES
   

Name ::

KOPILI HYDRO ELECTRIC PLANT

   

Capacity ::

200 MW + 50 MW + 25 MW = 275 MW

   

Location ::

Umrongso, District-North Cachar Hills, ASSAM, PIN - 788931

   

Approach ::

By Road - 140 Km from Shillong, 70 Km from Lanka Railway Station in Assam

   

Design Energy ::

1550 MU

 

 
Date of Commissioning :: Khandong Unit-I 8-March-1984
Khandong Unit-II 3-May-1984
Kopili Unit-I 4-July-1988
Kopili Unit-II 21-July-1988
Kopili Unit-III 5-March-1997
Kopili Unit-IV 17-June-1997
KHEP Stg-II
26-July-2004 (Date of Commercial Operation)
   
Beneficiary States :: Assam, Arunachal Pradesh, Manipur, Meghalaya, Mizoram, Nagaland and Tripura.
   

Technical Features ::

 
Kopili POWER STATION:

Dam

Type :: Concrete Gravity
Height :: 30 m
Length :: 143 m

Tunnel LP tunnel 4.6 m dia, 5.5 km long concrete lined.
HP tunnel 4.6 m dia 825.0 m long concrete liner & 4.0 m dia 300 m long steel liner .
Penstock Two nos. 2.7 m dia 890 m long bifurcated into 2 m dia, 43 m long steel liner.
Design Head 326.50 m


Evacuation System: 220 kV Kopili- Misa D/C Lines, 220 kV Kopili – Misa S/C Line, 132 kV Kopili-Khandong S/C Line.

 
Khandong POWER STATION & KHEP Stg-II:

Dam

Type :: Concrete Gravity
Height :: 66 m
Length
:: 243 m

Tunnel Concrete lined 4.5 m dia 2852 m long and 4.5 m dia 38 m steel lined.
Penstock i) Two nos. 2.5 m dia & 192 m long.
ii) 3.2 m dia 275 m long and 2.5 m dia. 205 m long steel liner for stg-II
Design Head 99 m
 
Evacuation System : 132 kV Khandong-Haflong S/C Line, 132 kV Khandong-Khliehriat D/C Lines.
   
 
^ top

 
 
ACHIEVEMENT
 

 
 
 
 
^ top


 
 
STATUS OF GENERATION:
 

a)

Generation during May 2010

8.4

MU

b)

Generation during 2009-2010( 01/04/2009 to 31/03/2010 )

930.67

MU

 

 

 

 
^ top
 

 
CONTACT PERSON
 
HEAD OF PROJECT
Project Head: Hemant Kumar Deka
Designation : GM(E/M)
Telephone (O) 03670 288222
Telephone (R) 03670 288223