The Pare Hydro Electric Project (2 x 55 MW) is planned as a R-o-R scheme on the Dikrong River downstream of the powerhouse of the first stage of the Ranganadi Hydro Electric Project in the Papumpare District of Arunachal Pradesh. This project is part of the Dikrong - Panyor Development Scheme located in the state of Arunachal Pradesh. A concrete diversion dam of 78 m height is proposed to be constructed. The water from the reservoir thus created will be carried through a 2.81 Km long, 7.5 m dia modified horseshoe shaped Head Race tunnel for feeding 2 units of 55 MW each. CEA has accorded TEC to the project on 24-9-2007 , as per which the project will generate annually 506.42 MU of power. CCEA has cleared the Project for implementation on 06-11-2008 , with total cost of Rs. 574.00 Crs. (including IDC at June, 2007 Price Level) with 1st year & Levellised Tariff of Rs. 2.49 and Rs. 2.11 per unit respectively. Project is scheduled for commissioning in 44 months time from date of CCEA Clearance.

SALIENT FEATURES
Name PARE HYDRO ELECTRIC PROJECT
Location

Arunachal Pradesh, Papumpare District

Approach

The nearest Airport is North Lakhimpur and the nearest Rail Head is North Lakhimpur (MG).

Capacity

110 MW ( 2X55 )

Energy Generation

506.42 MU

Project Cost

Rs. 573.99 Crs

Date of CCEA Clearance

04-12-2008

Tariff Rate Levellised tariff : Rs 2.11/Unit, 1st Year tariff : Rs 2.49/Unit
Year of Commissioning /Completion Schedule
44 months from the date of CCEA clearance.
^top
 
LAYOUT  
 
TECHNICAL FEATURES PARE HYDRO ELECTRIC PROJECT
 
  • Height of Concrete Gravity Dam on Pare River = 78 m
  • Length of HRT (having 7.5 m dia. Modified Horse Shoe Shape Tunnel) =2.81 Km.
  • Surge Shaft (Restricted Orifice Type) having 15m dia and 58m depth and orifice diameter 3.0m.
  • Power House (surface): Size: 68 m x 23 m having 2 units of 55 MW each.
  • Type of Turbine: Vertical Francis Turbine.
 
^top
 
PRESENT STATUS AS ON 30.06.2010

 

Sl No.

              Activity

Unit

Total Qty.

Cumulative     Progress

Remarks

1

Diversion Tunnel:

Open Excavation

 

Cum

 

15000

(approx)

 

7300

 

Work hampered due to incessant rain.

2

Adit – I

Boring

 

Rm

 

112

 

83.50

Work is in progress.

 

3

Adit – II

Boring

 

Rm

 

84

 

51.50

 

Work is in progress.

4

Surge Shaft:

Open Excavation

 

Cum

 

70000

(approx)

 

41896

 

Work is in progress.

 

5

 

Open excavation of power house

 

Cum

 

 66690

(approx)

 

15111

 

Work is in progress.

Status of Tender and Award of Works:

Sl No

Particulars

Date of LOI/ Work order

            Remarks

1

Design and Review Consultancy Work

16.02.2010

(W.O)

Work order issued to M/s SNC-Lavalin Inc., on 16.02.2010.

 

2

Package – I (Main Civil Works)

23.09.2009

(W.O)

Contract Agreement was drawn with M/s HCC Ltd. on 12.10.2009

3

Package – II

 (Hydro-Mechanical Works)

 

Techno- Commercial bid opened on 09.09.09.Techno-commercial bids evaluation completed. Concurrence obtained from Kfw and SNC-Lavalin (consultant). Price Bid opened on 25.03.10 and evaluation completed. Concurrence obtained from SNC-Lavalin and Concurrence from Kfw is awaited. Award of work is under process.

 

4

Package – III (Electro-Mechanical Equipments)

 

Techno- Commercial bid opened on 18.09.09. Techno-commercial bids evaluation completed. Concurrence of Kfw obtained. Price bid opened on 24.03.2010 and evaluation completed. Concurrence obtained from SNC-Lavalin and Concurrence from Kfw is awaited. Award of work is under process.

5

Package – IV

 (Transformer & Switchyard)

 

NIB floated on 24.02.2010. Techno-Commercial bid opened on 11.06.10 and evaluation is in progress.

6

Construction of  Rope Way Suspension Bridge (span: 120m)

06.01.2010

(LOI)

LOI for Ropeway suspension Bridge from Chiputa to Ross village has been issued on 06.01.2010 to M/S Tagar construction Agency. Completion time is 6 months from the date of issue of LOI. Progress is hampered severely due to heavy rain.

7

Construction Power

 

 

i)

Construction of 33 kv line

28.07.09

(W.O)

W.O for 33kv line placed on 28.07.09. Supply of all line materials for construction of 33 kv line completed. In principle approval of Forest clearance obtained from MOEF, Govt. of India, Shillong on 07.05.10. Matter is being pursued with the state Govt. for final clearance. Proposal for payment of NPV is under process and will be released shortly.

ii)

Construction of associated 11 kv line

30.03.2010

(W.O)

Detailed work order for associated 11 kv line at Dam and power house sites has been issued to M/s Tana Pekhi, Midpu village, Doimukh, AP on 30.03.10. Erection of the same is in progress.

iii)

Construction of 33/11 KV Sub- Station

 

LOI for construction of 33/11 KV Sub-station has been placed on 06.05.10. Construction drawings have already been approved.

iv)

Procurement of 2x250 KVA DG Set

19.02.2010

(W.O)

The W.O for procurement of 1(one) no each 250 & 125 KVA DG Set from OEM for power supply at Jampa and Sopo site has already been issued to M/s Surav Auto Pvt. Ltd., Guwahati on 19.02.2010. The materials has been delivered at site. Erection and commissioning of the same is completed on 31.05.2010.

^top
CONTACT PERSON
Name:

Mr. D. Mukherjee, GM

Designation: Head of Project, Pare HEP
Tel No:

0360-2278252

Email : hoppare@neepco.gov.in
^top
Click on this Link For a Detailed Photo Gallery of Kameng Hydro Electric Project
 
 

|| About Us | Completed Projects | On Going Projects | Future Projects | Commercial | Chairman's & Directors' Reports | Neepco's Socio Economic Contibution | Environment | Events | Power Potential in the North East | Tender Notices | Feedback | MOU | RTI ||

Neepco home Page HOME         BackBACK