| A Profile |
| |
|
| |
|
INTRODUCTION
|
This Project is located in the Lower Subansiri District of the State of Arunachal Pradesh in the Ranganadi basin and the adjoining Dikrong basin.
|
| |
 |
Overview of Ranganadi Project |
|
| |
|
^ top |
|
| |
| |
| |
| |
| FEATURES |
| |
| Name :: |
RANGANADI HYDRO ELECTRIC PLANT |
| |
|
| Capacity :: |
405 MW (3 X 135) |
| |
|
| Location :: |
Yazali, District-Lower Subansiri,Arunachal Pradesh, PIN - 791119 |
| |
|
| Approach :: |
By Road 90 KM From North Lakhimpur in Assam |
| |
|
| Design Energy :: |
1510 MU |
| |
|
| Date of Commissioning :: |
Unit - I |
26-January-2002 |
| Unit - II |
29-January-2002 |
| Unit - III |
27-March-2002 |
| |
|
| Beneficiary States :: |
Assam, Arunachal Pradesh, Manipur, Meghalaya, Mizoram, Nagaland and Tripura |
| |
|
| Technical Features :: |
|
| |
| Dam |
Type :: Concrete Gravity
Height :: 68 m
Length :: 340 m
|
| Tunnel |
HR Tunnel
6.8 m dia, 10.13 km long
Pr. Tunnel
5.8 m dia, 778 m long.
4.75 m dia, 137 m long.
3.35 m dia, 147 m long. |
| Penstock |
| Design Head |
304.0 m |
|
|
| |
| |
Evacuation System :: 400 kV Ranganadi-Balipara D/C Lines, 132 kV Ranganadi-Nirjuli S/C Line, 132 kV Ranganadi-Along S/C Line. |
|
|
| |
| |
| |
| ACHIEVEMENT |
| |

|
|
| |
3 X 135 MW Ranganadi HEP has been selected for NATIONAL AWARDS for the year 2004-05 for meritorious performance in Power Sector initiated by MOP, GOI. |
| |
RHEP generated 9.829 MU of Electric Energy on 19 June 2007 , the highest ever generated of the plant in a single day. |
|
| |
|
| |
| |
| |
| STATUS OF GENERATION : |
| |
a) |
Generation during December 2008 |
: |
56 MU |
b) |
Generation during 2007-2008( 01/04/07 to 31/03/08 ) |
: |
1540 MU |
|
|
|
|
| |
|
| |
| |
| |
| CONTACT PERSON |
| |
HEAD OF PROJECT |
Project Head |
M.S. Jyrwa |
Designation |
General Manager(E/M) |
Telephone (O) |
03809-222204/222256 |
Telephone (R) |
03809-222230/222216 |
E-Mail |
hoprhep@neepco.gov.in |
|
| |
|